Configuration

The settings that shape ERPNext TaskView, the hook that chooses which Timesheet receives time, and a reference of everything the app adds to a site.

Updated
On this page

TaskView has no settings page of its own. It is configured through fields on documents you already use, a few standard ERPNext settings, and one hook for developers. This page lists them, then lists everything the app adds to your site.

For staff and project managers

SettingWhereWhat it does
Expected Time (in hours)Task formThe task's hour budget. Without one, the task uses the sum of its subtasks. See Hour budgets.
Budgeted HoursProject form, below Estimated CostThe project's hour budget. Without one, the project uses the sum of its top-level tasks.
User IDEmployee formTimers log to the Employee whose User ID is the person's login, so each person who times work needs one.
CustomerProject formDecides which customer's contacts and portal users can see the project in the client portal.

The side panel in Task View opens the Task or Project form, so these are one click from the tree.

For administrators

SettingWhereWhat it does
Customer accessCustomer: Portal Users; Contact linked to the Customer; Project: UsersWho may open which project on the portal. See Giving customers access.
Default Portal Home, Portal MenuPortal SettingsWhere customers land after signing in, and whether ERPNext's own Projects row (/project) is still listed. A fresh install leaves both to you: see Install and upgrade.
Client Portal Notification TypeNotification TypeThe kind of notification the team receives when a customer acts on the portal. Whether it also goes out by email follows each user's Notification Settings.
Outgoing emailEmail AccountNotification emails need your site's outgoing email to be set up. This was not tested for these docs.
Ignore User Time Overlap, Ignore Employee Time OverlapProjects SettingsBoth must be ticked for timers to work. A paused timer's time log overlaps the timer that ran in the meantime, and ERPNext otherwise refuses the Timesheet. See Allow overlapping time logs.
File size limitSite configurationThe portal rejects files over 25 MB in the browser and leaves the real limit to your site's own file size setting.

Some behaviour is fixed in the code and cannot be changed from the desk: the four board columns (Open, Working, Pending Review, Completed), the portal's list of accepted file types for customers, the limits of 60 new tasks, 60 comments and 60 uploads per hour from one IP address, and the one-minute refresh of an open project. The client portal describes each.

Choose which Timesheet receives time

By default, a timer adds its time to the draft Timesheet that matches the Employee and the project, and creates one when there is none. A developer can replace that choice with the taskview_find_timesheet hook, for example to keep one Timesheet per calendar month per project.

The hook is called with the keyword arguments employee and project and returns the name of a draft Timesheet to reuse, or None to create a new one. employee is None when the user has no Employee. If several apps register the hook, the last registered one is used.

# hooks.py of your own app
taskview_find_timesheet = "my_app.timesheets.find_timesheet"
# my_app/timesheets.py
import frappe


def find_timesheet(employee: str | None, project: str) -> str | None:
	return frappe.db.exists(
		"Timesheet",
		{"employee": employee, "parent_project": project, "docstatus": 0},
	)

Name the parameters employee and project exactly: TaskView passes them by keyword. Return only a Timesheet that is still a draft, because the timer appends a row to whatever you return and saves it.

What the app adds to your site

This is the complete list, so you can see what a bench migration changes.

Fields and property settings

DocumentChange
ProjectA Budgeted Hours field (budgeted_hours, Float, not negative) after Estimated Cost. Its description reads "Hours budgeted for the whole project. Leave 0 to use the sum of the task estimates."
ProjectDefault view set to Task View. Customer is shown in the list view, the standard filters, the filters and the preview.
TaskDefault view set to Task View. Track Changes is switched on, which records the status changes the portal's activity feed shows. Show Title Field in Link is switched on.
Timesheet DetailFour read-only fields: Paused, Start Time, Paused Time (paused_time_in_seconds, editable after submit) and Task Subject (fetched from the task). They hold the timer state.
ToDoA read-only Pinned check (pin) after Priority. Pinned tasks are ToDos with this box set.

Behaviour

WhereChange
TaskThe Task class is extended so that the portal can save a task, close its assignments and update its parent and dependent tasks on behalf of a customer, who holds no Task permission. Saves that do not ignore permissions take ERPNext's normal path.
TimesheetSubmitting a Timesheet moves a task forward only: Open becomes Working, and a task in Pending Review or Completed stays where it is. ERPNext's own code would set every task back to Working.
Timesheet DetailThe class carries the typed timer fields above.
Notification TypeA Client Portal type is created when the app is installed or the site is migrated.
Website/projects and everything under it is served by the portal. The portal menu gets a Projects entry for users with the Customer role. /project redirects to /projects.
DeskThe Task View and timer dock bundles load on every desk page.